if 12 people can finish a job by 5 days how many days will be required finish the same job by 10 people

Respuesta :

ishashunnny
ishashunnny ishashunnny
  • 01-09-2020

Answer:

4

Step-by-step explanation:

12p=5d

1p=5/12

10p=4.1666

≈4 days

Answer Link

Otras preguntas

Score Frequency 1| 0 2| 3 3| 4 4| 16 5| 22 Scores on an AP Exam at a local high school are recorded in the table. What was the average score? A) 0.234 B) 3
Tell me everything I need to know about Anthem by Ayn Rand. Summaries , answers to possible questions, things you found out after reading , etc.
whats the answer of 8/25
Why did people migrate from Asia to the Americas
What is a function of families for individuals and societies? A. Protection B. Socialization C. Affection D. All of the above
How did the collapse of the western roman empire lead to a new age in western europe?
Find the missing angle and classify each triangle as acute, obtuse, or right
What are the essential tools for a writer?
Train A and train B leave the central station at the same time.They travel the same sped,but in opposite directions,with train A heading towards station A, and
Why do you think jamestown colony was built in a triangular shape?