Is typically not referred to as a buffer type in critical chain project management?

Respuesta :

dinosaurbarn
dinosaurbarn dinosaurbarn
  • 14-01-2018

The answer is Free Buffer. Project buffer, a not usual and the only one buffer to protect the project deadline;

Feeding buffer it is different types of buffers to protect parts of the critical chain. And resource buffer is a multiple artificial buffers that act as warning signals to assure that it is available of resources.

Answer Link

Otras preguntas

what is a quotient of 396 divided by 12
1. There are 100 cm in 1 m and 1000 m in 1 km. You need a curtain for a window that is 156 cm wide. (a) If you wanted to convert the width to kilometers, what
how did the political goals of liberals differ from those of conservatives
Why did merchants create joint-stock companies and use cottage industries? FIVE SENTENTCES
5.125 − 0.080 = _______. A. 5.044 B. 0.045 C. 0.045 D. 5.045
Why did kings want their colonies to trade only with the mother country?
What mechanical devices are used to restrain cats?
what were three facts about germanys attack that shirer recorded in his diary entry? what were three opinions he wrote down?
The symbol, 1, in binary code means that the transistors are _______. A. Open or on B. Closed or off C. Neither D. Both A & B
Which of the following is a lower chamber of the heart? A.Atrium B.Pacemaker C.Septum D.Ventricle